Question 421 - PMP discussion
After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration. At this point, the project manager learns about a possible change in regulations that would prevent the product launch.
What should the project manager do to realize benefits?
A.
Add an entry in the risk log
B.
Implement the changes
C.
Review target benefits
D.
Improve the team's velocity
Your answer: