Question 423 - PMP discussion

Report
Export

A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.

Which two actions should the team take to engage this new team member? (Choose two.)

A.
Revisit the team's discussion on team behaviors and norms
Answers
A.
Revisit the team's discussion on team behaviors and norms
B.
Report to the project manager about the new team member's behavior
Answers
B.
Report to the project manager about the new team member's behavior
C.
Coach the new team member to improve engagement with the team
Answers
C.
Coach the new team member to improve engagement with the team
D.
Force the new team member to participate in activities that are considered easy
Answers
D.
Force the new team member to participate in activities that are considered easy
E.
Facilitate an open discussion on all ideas and perspectives
Answers
E.
Facilitate an open discussion on all ideas and perspectives
Suggested answer: C, E