A company wants to increase the commercial value of one of its products in a highly competitive market. In order to do this, the company commissions a project to create a prototype. The team constructs the prototype incrementally.

Which action should the project manager take as a priority?

A.
Emphasize the use of Kanban methodology
Answers
A.
Emphasize the use of Kanban methodology
B.
Ensure the project sponsor is aware of the go-to market date
Answers
B.
Ensure the project sponsor is aware of the go-to market date
C.
Deliver business value as soon as possible
Answers
C.
Deliver business value as soon as possible
D.
Implement a plan-do-check-act (PDCA) cycle
Answers
D.
Implement a plan-do-check-act (PDCA) cycle
Suggested answer: D