During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task.

What should the project manager do?

A.
Ask the new team member to follow the team ground rules
Answers
A.
Ask the new team member to follow the team ground rules
B.
Ask an experienced team member to identify a replacement
Answers
B.
Ask an experienced team member to identify a replacement
C.
Ask the new team member to reassess their own capabilities
Answers
C.
Ask the new team member to reassess their own capabilities
D.
Ask an experienced team member to coach the new team member
Answers
D.
Ask an experienced team member to coach the new team member
Suggested answer: D