Question 434 - PMP discussion

Report
Export

A technical manager newly appointed by the client, visits the project site to verify the project deliverables. The technical manager feels that the project manager has not been providing enough information.

What should the project manager do first to resolve this situation?

A.
Update the issue log and escalate to the project sponsor
Answers
A.
Update the issue log and escalate to the project sponsor
B.
Identify the lack of information as a risk and update the risk register
Answers
B.
Identify the lack of information as a risk and update the risk register
C.
Schedule more frequent meetings with the technical manager
Answers
C.
Schedule more frequent meetings with the technical manager
D.
Review and update the stakeholder engagement plan
Answers
D.
Review and update the stakeholder engagement plan
Suggested answer: D
asked 23/09/2024
Sathish M
48 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first