During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version.

How can the project manager prevent this outcome in the new project?

A.
Hire a team of external users to perform acceptance testing on the product
Answers
A.
Hire a team of external users to perform acceptance testing on the product
B.
Define a user focus group as external stakeholders with a high influence on outcomes
Answers
B.
Define a user focus group as external stakeholders with a high influence on outcomes
C.
Hire a consultant to perform a benefit analysis as an input to the project charter
Answers
C.
Hire a consultant to perform a benefit analysis as an input to the project charter
D.
Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS)
Answers
D.
Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS)
Suggested answer: B