A project manager is leading a project with several stakeholders in other functional areas of the company. One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project.

What should the project manager have the project team update to ensure proper communications to stakeholders?

A.
Project management plan
Answers
A.
Project management plan
B.
Stakeholder engagement plan
Answers
B.
Stakeholder engagement plan
C.
Stakeholder register
Answers
C.
Stakeholder register
D.
Communications management plan
Answers
D.
Communications management plan
Suggested answer: B