Question 457 - PMP discussion
A project manager is in rapid development mode on a joint application development module. The company wants delivery to occur in two weeks. The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog.
What should the project manager do?
A.
Push the team to deliver more so that the modules are developed and rolled out according to management's request
B.
Speak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined
C.
Have the team work toward the tighter deadline so that integration will be easier
D.
Speak to the team and slow the current pace to ensure the team is in alignment with the release date
Your answer: