During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested.

What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?

A.
Include stakeholders during daily standup meetings to monitor progress
Answers
A.
Include stakeholders during daily standup meetings to monitor progress
B.
Validate acceptance criteria with stakeholders prior to backlog refinement
Answers
B.
Validate acceptance criteria with stakeholders prior to backlog refinement
C.
Avoid including stakeholders in iteration reviews
Answers
C.
Avoid including stakeholders in iteration reviews
D.
Create a requirements traceability matrix and distribute it accordingly
Answers
D.
Create a requirements traceability matrix and distribute it accordingly
Suggested answer: B