Question 461 - PMP discussion

Report
Export

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals.

What two options will help the team initially address this obstacle? (Choose two.)

A.
Escalate the issue to the project sponsor
Answers
A.
Escalate the issue to the project sponsor
B.
Review and update dependencies
Answers
B.
Review and update dependencies
C.
Schedule a retrospective
Answers
C.
Schedule a retrospective
D.
Conduct a root cause analysis
Answers
D.
Conduct a root cause analysis
E.
Create a risk management plan
Answers
E.
Create a risk management plan
Suggested answer: B, D