Question 480 - PMP discussion

Report
Export

A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria.

What should the project manager do?

A.
Persuade this stakeholder using emotional intelligence skills to obtain acceptance.
Answers
A.
Persuade this stakeholder using emotional intelligence skills to obtain acceptance.
B.
Obtain final acceptance from another stakeholder who is also familiar with the project.
Answers
B.
Obtain final acceptance from another stakeholder who is also familiar with the project.
C.
Escalate this issue to the project sponsor and ask for support in obtaining final stakeholder acceptance.
Answers
C.
Escalate this issue to the project sponsor and ask for support in obtaining final stakeholder acceptance.
D.
Create a project acceptance waiver noting the stakeholder's concerns so they can be addressed later.
Answers
D.
Create a project acceptance waiver noting the stakeholder's concerns so they can be addressed later.
Suggested answer: C