Question 482 - PMP discussion
During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy.
How should the project manager reflect this change in the project?
A.
Update the communication styles for enrolled team members in the communications management plan.
B.
Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM).
C.
Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.
D.
Update the resource calendar for enrolled team members in the resource management plan.