Question 486 - PMP discussion
A team is holding the first demonstration of the software built to date on a medium-sized project.
The product owner has uncovered a number of issues they would like to be addressed before providing approval.
How should the project manager approach this problem?
A.
Plan to address the issues through backlog grooming and incorporate them into the next sprint
B.
Refer the product owner to the change management plan, then escalate to the steering committee
C.
Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes
D.
Tell the product owner the issues will be addressed in the second version of the software
Your answer: