A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach.
What should the project manager do to ensure full compliance of quality requirements during the execution phase?
A.
Analyze the quality requirements.
B.
Plan quality management
C.
Continually survey the quality of the deliverable
D.
Set up quality policies and procedures