A project manager accepts a delivery at the project site but the items are of a poor quality. The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected.

What should the project manager do going forward?

A.
Allocate extra time to inspect deliveries for quality assurance upon arrival at the site
Answers
A.
Allocate extra time to inspect deliveries for quality assurance upon arrival at the site
B.
Review the contract requirements and ask for the applicable evidence for quality assurance
Answers
B.
Review the contract requirements and ask for the applicable evidence for quality assurance
C.
Have the vendor issue the quality documentation prior to the next delivery
Answers
C.
Have the vendor issue the quality documentation prior to the next delivery
D.
Call the vendor and have them verbally guarantee the quality of the next site delivery
Answers
D.
Call the vendor and have them verbally guarantee the quality of the next site delivery
Suggested answer: B