ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 534 - PMP discussion

Report
Export

HOTSPOT

A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.

Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck.


Question 534
Correct answer: Question 534
asked 23/09/2024
jose fajardo
30 questions
User
0 comments
Sorted by

Leave a comment first