ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 542 - PMP discussion

Report
Export

DRAG DROP

A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.

Question 542
Correct answer: Question 542

Explanation:

Explanation:

asked 23/09/2024
Leila Bekirova
39 questions
User
0 comments
Sorted by

Leave a comment first