Question 544 - PMP discussion

Report
Export

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches.

What does the project manager need to do first in order to have good project performance?

A.
Coach those team members lacking hybrid knowledge to learn on the job.
Answers
A.
Coach those team members lacking hybrid knowledge to learn on the job.
B.
Change the team to include hybrid experts.
Answers
B.
Change the team to include hybrid experts.
C.
Assess the required training per team member.
Answers
C.
Assess the required training per team member.
D.
Deliver hybrid training to all team members.
Answers
D.
Deliver hybrid training to all team members.
Suggested answer: C