Question 563 - PMP discussion
A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?
A.
Ask for expedited delivery of the component to mitigate the risk of schedule delays
B.
Ensure that relevant stakeholders and expectations are identified and assess the component delay
C.
Perform a detailed analysis of the release content for each component of the solution
D.
Propose a new design of the solution maw the external component with an internal one
Your answer: