A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.
Which estimation technique should the project manager recommend?
A.
Analogous estimating
B.
Parametric estimating
C.
Planning poker
D.
Three-point estimating