A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.

Which estimation technique should the project manager recommend?

A.
Analogous estimating
Answers
A.
Analogous estimating
B.
Parametric estimating
Answers
B.
Parametric estimating
C.
Planning poker
Answers
C.
Planning poker
D.
Three-point estimating
Answers
D.
Three-point estimating
Suggested answer: D