Question 578 - PMP discussion
A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.
What should the project manager do next?
A.
Take on some of the necessary work to minimize the impact.
B.
Invite the stakeholders to discuss a mitigation plan.
C.
Detail the reason for the project delay in the status report.
D.
Register an issue and escalate it to the project sponsor.
Your answer: