An agile project for a database migration impacts nearly all business units of the corporation.

Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.

What should the product owner do about this situation?

A.
Reprioritize the backlog based on value and cost of delay divided by duration.
Answers
A.
Reprioritize the backlog based on value and cost of delay divided by duration.
B.
Switch to a predictive approach to prevent any further delays to completion.
Answers
B.
Switch to a predictive approach to prevent any further delays to completion.
C.
Reprioritize the backlog based on story size and competence availability.
Answers
C.
Reprioritize the backlog based on story size and competence availability.
D.
Remove low-value items from the backlog to compensate for the higher cost.
Answers
D.
Remove low-value items from the backlog to compensate for the higher cost.
Suggested answer: D