Question 589 - PMP discussion
An agile project for a database migration impacts nearly all business units of the corporation.
Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.
What should the product owner do about this situation?
A.
Reprioritize the backlog based on value and cost of delay divided by duration.
B.
Switch to a predictive approach to prevent any further delays to completion.
C.
Reprioritize the backlog based on story size and competence availability.
D.
Remove low-value items from the backlog to compensate for the higher cost.