Question 595 - PMP discussion
An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project.
What should the project lead do?
A.
Ask that estimations be provided only by senior developers.
B.
Recommend a different estimation method in the retrospective.
C.
Allocate more time for estimation in the sprint planning.
D.
Review and update the estimations in the daily standup.