Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.
What should the project manager do?
A.
Reschedule on-site training to online sessions.
B.
Document the project issue and provide options.
C.
Create a risk and assign remediation actions.
D.
Cancel all of the on-site training sessions.