A distributed project team has communication issues because of their collaboration tools. The team feels that efficiency could be improved by changing the collaboration platform.

What should the project manager do?

A.
Implement the communication tools used by other project teams.
Answers
A.
Implement the communication tools used by other project teams.
B.
Escalate the issue to the sponsor and ask them to decide.
Answers
B.
Escalate the issue to the sponsor and ask them to decide.
C.
Inform the project team to continue using the current tools.
Answers
C.
Inform the project team to continue using the current tools.
D.
Discuss this with the project team and select the appropriate tools.
Answers
D.
Discuss this with the project team and select the appropriate tools.
Suggested answer: D