ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 637 - PMP discussion

Report
Export

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

A.
Probabilistic analysis was used to develop the budget to address future uncertainties.
Answers
A.
Probabilistic analysis was used to develop the budget to address future uncertainties.
B.
The budget was developed by using the lessons learned from previous project data.
Answers
B.
The budget was developed by using the lessons learned from previous project data.
C.
Recurrent team meetings are planned to control the budget against future uncertainties.
Answers
C.
Recurrent team meetings are planned to control the budget against future uncertainties.
D.
Feedback from stakeholders will be addressed at each board meeting to adapt the budget.
Answers
D.
Feedback from stakeholders will be addressed at each board meeting to adapt the budget.
Suggested answer: B
asked 23/09/2024
Istvan Molnar
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first