A company's key product is evolving and requires the use of a new technology. No one on the team is familiar with this technology; however, experienced developers on the team volunteered to study the concepts and application and believe they will be able to take full responsibility for the new technology.

What should the project manager do?

A.
Outsource the technology work to a third party so as not to delay work.
Answers
A.
Outsource the technology work to a third party so as not to delay work.
B.
Descope this requirement as the developers have more important tasks.
Answers
B.
Descope this requirement as the developers have more important tasks.
C.
Hire externally since the internal developers already have assigned work.
Answers
C.
Hire externally since the internal developers already have assigned work.
D.
Support the developers with their intention to learn the new technology.
Answers
D.
Support the developers with their intention to learn the new technology.
Suggested answer: D

Explanation:

Support the developers with their intention to learn the new technology. Project managers should provide resources and support to the developers to ensure they are successful in their learning and application of the new technology.

Outsourcing the work, descoping the requirement, or hiring externally are not recommended solutions in this case.