A project manager is assigned to a new project. The project is for a new product that the company wants to launch as soon as possible to test market readiness. The project is part of a large business transformation, and the objective is to open delivery channels for the new product.
Which delivery approach should the project manager recommend?
A.
A predictive approach with an experienced project team.
B.
An adaptive approach with clearly defined user stories.
C.
An adaptive approach with loosely defined large epics.
D.
A predictive approach with clear acceptance criteria.