A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

A.
Review the communications management plan to identify new stakeholders.
Answers
A.
Review the communications management plan to identify new stakeholders.
B.
Define a risk management plan for the new approach, as needed.
Answers
B.
Define a risk management plan for the new approach, as needed.
C.
Define a project management plan for the new approach, as needed.
Answers
C.
Define a project management plan for the new approach, as needed.
D.
Review the benefits realization plan to include the cost of the change.
Answers
D.
Review the benefits realization plan to include the cost of the change.
Suggested answer: D