A project manager holds periodic progress review meetings to discuss issues.

What should the project manager do first on the agenda?

A.
Elaborate the risk mitigation strategy and risk register.
Answers
A.
Elaborate the risk mitigation strategy and risk register.
B.
Update resolution approaches and action assignments.
Answers
B.
Update resolution approaches and action assignments.
C.
Formulate project management plan integration.
Answers
C.
Formulate project management plan integration.
D.
Produce lessons learned documentation.
Answers
D.
Produce lessons learned documentation.
Suggested answer: B