During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.

Which of the documents was likely missed or outdated?

A.
Stakeholder Register
Answers
A.
Stakeholder Register
B.
Risk Register
Answers
B.
Risk Register
C.
Project Charter
Answers
C.
Project Charter
D.
Business Documentation
Answers
D.
Business Documentation
Suggested answer: A