Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.

What should the project manager do next?

A.
Apply appropriate conflict resolution techniques to solve the issue.
Answers
A.
Apply appropriate conflict resolution techniques to solve the issue.
B.
Engage in individual conversation with each team member.
Answers
B.
Engage in individual conversation with each team member.
C.
Call a team meeting to have a formal discussion of the issue.
Answers
C.
Call a team meeting to have a formal discussion of the issue.
D.
Allow the team to work through it on their own unless help is needed.
Answers
D.
Allow the team to work through it on their own unless help is needed.
Suggested answer: A