List of questions
Related questions
Question 658 - PMP discussion
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
A.
Reach an agreement with the team on how to handle the situation.
B.
Allow senior management to decide how to proceed with the project.
C.
Reach out to the procurement team to hire a substitute for the team member.
D.
Convince the team member not to leave until the project is completed.
Your answer:
0 comments
Sorted by
Leave a comment first