A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change.

What should the project manager do?

A.
Seek advice from the legal department and implement penalties.
Answers
A.
Seek advice from the legal department and implement penalties.
B.
Search for a new supplier that can deliver the same materials on time.
Answers
B.
Search for a new supplier that can deliver the same materials on time.
C.
Tell the supplier that they have an obligation to supply the raw material.
Answers
C.
Tell the supplier that they have an obligation to supply the raw material.
D.
Assess the possible impact of the raw material shortage on the project.
Answers
D.
Assess the possible impact of the raw material shortage on the project.
Suggested answer: D