A project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved, the project manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.

What should the project manager review during the management review to ensure the meeting is effective?

A.
Specialized reports created specifically for the meeting as per directions from the project sponsor.
Answers
A.
Specialized reports created specifically for the meeting as per directions from the project sponsor.
B.
Potential changes to the project's strategy and the feedback from senior executives.
Answers
B.
Potential changes to the project's strategy and the feedback from senior executives.
C.
The deliverables that are performing well and those that need more work.
Answers
C.
The deliverables that are performing well and those that need more work.
D.
Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.
Answers
D.
Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.
Suggested answer: D