A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.

What should the project manager do to improve the situation?

A.
Ask the construction manager to meet with the two team members to resolve the situation.
Answers
A.
Ask the construction manager to meet with the two team members to resolve the situation.
B.
Discuss the team members' concern with the construction manager and seek solutions.
Answers
B.
Discuss the team members' concern with the construction manager and seek solutions.
C.
Ask the team members to tolerate the cultural differences as they have a different cultural background.
Answers
C.
Ask the team members to tolerate the cultural differences as they have a different cultural background.
D.
Provide the construction manager with instructions on how to resolve the situation.
Answers
D.
Provide the construction manager with instructions on how to resolve the situation.
Suggested answer: B