A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.

What should the project manager do?

A.
Assign actions to all stakeholders and oversee their implementation.
Answers
A.
Assign actions to all stakeholders and oversee their implementation.
B.
Acknowledge the impediments and facilitate their resolutions.
Answers
B.
Acknowledge the impediments and facilitate their resolutions.
C.
Note the impediments and escalate them to the product owner.
Answers
C.
Note the impediments and escalate them to the product owner.
D.
Note the impediments and work on addressing them later.
Answers
D.
Note the impediments and work on addressing them later.
Suggested answer: B