List of questions
Related questions
Question 704 - PMP discussion
A project manager is leading a hybrid project that is building an app for a travel industry startup.
Due to unforeseen events, the features and the overall solution will not be useable by many customers due to new travel restrictions.
What should the project manager do first?
A.
Release the team and help them achieve their potential on a new project.
B.
Pause the project if business value cannot be reached and collect lessons learned.
C.
Assess the environmental changes and recommend a pivot for the project.
D.
Ask the organization's management for advice regarding the project's direction.
Your answer:
0 comments