ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 707 - PMP discussion

Report
Export

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months.

What should the project manager do first?

A.
Set up a steering committee session to review the project delay.
Answers
A.
Set up a steering committee session to review the project delay.
B.
Continue with the approved design so that the project is not delayed.
Answers
B.
Continue with the approved design so that the project is not delayed.
C.
Log the technical design delay as a risk in the project risk log.
Answers
C.
Log the technical design delay as a risk in the project risk log.
D.
Ask the steering committee to approve a new technical design.
Answers
D.
Ask the steering committee to approve a new technical design.
Suggested answer: C
asked 23/09/2024
Najim Abdelmoula
46 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first