A project manager has received feedback from stakeholders regarding poor communication about project progress. Weekly status reports were provided to the project management office (PMO), and the standard communications management plan was followed.

What should the project manager do?

A.
Create a change request for implementing an online collaboration tool.
Answers
A.
Create a change request for implementing an online collaboration tool.
B.
Distribute hard copies of status reports and confirm that messages were read.
Answers
B.
Distribute hard copies of status reports and confirm that messages were read.
C.
Perform a root cause analysis (RCA) of the existing communication approach.
Answers
C.
Perform a root cause analysis (RCA) of the existing communication approach.
D.
Ensure that all of the complaining stakeholders are on the distribution list.
Answers
D.
Ensure that all of the complaining stakeholders are on the distribution list.
Suggested answer: C