A customized module is being implemented into an off-the-shelf enterprise resource planning (ERP) solution. The project scope has been clearly defined by the sponsor, and the project manager is close to starting user acceptance testing.

However, the newly elected government introduced a significant package of taxation reforms.

What should the project manager do?

A.
Contact the finance team and ask for advice.
Answers
A.
Contact the finance team and ask for advice.
B.
Put the project on hold and wait for information.
Answers
B.
Put the project on hold and wait for information.
C.
Assess the potential impact with the project team.
Answers
C.
Assess the potential impact with the project team.
D.
Continue with user testing as planned.
Answers
D.
Continue with user testing as planned.
Suggested answer: C