Question 721 - PMP discussion

Report
Export

As part of a company's planning effort for team capacity building, the project manager was asked to provide management with a list of required trainings for the project team.

What should the project manager do?

A.
Review the gaps found during project execution, prepare a list of recommended trainings, and discuss it during a team meeting.
Answers
A.
Review the gaps found during project execution, prepare a list of recommended trainings, and discuss it during a team meeting.
B.
Review the project schedule and the team members' performance, and decide on soft skills and related trainings needed for the team.
Answers
B.
Review the project schedule and the team members' performance, and decide on soft skills and related trainings needed for the team.
C.
Review the project pipeline, identify gaps in competencies for execution, and decide on the needed trainings.
Answers
C.
Review the project pipeline, identify gaps in competencies for execution, and decide on the needed trainings.
D.
Review the team members' latest performance, identify gaps in competencies, and decide on the needed trainings.
Answers
D.
Review the team members' latest performance, identify gaps in competencies, and decide on the needed trainings.
Suggested answer: C