An agile leader notices that one team member consistently fails to complete the deliverables on time. The agile leader suspects that this team member does not have the proper training.
What should the agile leader do?
A.
Reassign the task to another team member and require the team member to complete training
B.
Use the retrospective meeting to remind the entire team that they must complete all deliverables in each sprint
C.
Review the definition of done (DoD) with the team so that everyone understands what the team must deliver in this sprint.
D.
Speak directly with the team member about improvements and commit to an agreed-upon time frame.