Question 731 - PMP discussion
A project manager works at an organization that is transitioning to agile. The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.
What should the project manager do to ensure effective communication throughout the project?
A.
Advise the project management office (PMO) to use the burndown chart as the single communication channel.
B.
Develop a communications management plan for each category in the stakeholder register.
C.
Include the burndown chart in a monthly report that is distributed to all stakeholders.
D.
Postpone the recommendation since the organization does not currently have a defined agile methodology.
Your answer: