A project manager is managing a construction project that is facing challenges. There is schedule overrun, cost overrun, and the client is unhappy with the specific scope progress.
What should the project manager do first?
A.
Review the scope and project objectives.
B.
Enforce the penalty clause on the supplier.
C.
Take action to reduce the cost overrun.
D.
Work with the client on the scope completion.