Question 748 - PMP discussion
A project manager for an agile project is concerned that the team has been losing momentum over the last iterations.
Which two tools should the project manager use to analyze team performance? (Choose two.)
A.
Burndown chart
B.
Product backlog burnup chart
C.
Cumulative flow diagram of completed features
D.
Work breakdown structure (WBS)
E.
Project schedule