A project manager for an agile project is concerned that the team has been losing momentum over the last iterations.

Which two tools should the project manager use to analyze team performance? (Choose two.)

A.
Burndown chart
Answers
A.
Burndown chart
B.
Product backlog burnup chart
Answers
B.
Product backlog burnup chart
C.
Cumulative flow diagram of completed features
Answers
C.
Cumulative flow diagram of completed features
D.
Work breakdown structure (WBS)
Answers
D.
Work breakdown structure (WBS)
E.
Project schedule
Answers
E.
Project schedule
Suggested answer: A, C