A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.

Which life cycle should the project manager use for this project?

A.
A predictive execution strategy
Answers
A.
A predictive execution strategy
B.
An iterative execution strategy
Answers
B.
An iterative execution strategy
C.
An agile execution strategy
Answers
C.
An agile execution strategy
D.
A hybrid execution strategy
Answers
D.
A hybrid execution strategy
Suggested answer: D