Question 754 - PMP discussion

Report
Export

A new sales software development project is underway. The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.

Which project approach should the project manager take?

A.
Incremental
Answers
A.
Incremental
B.
Predictive
Answers
B.
Predictive
C.
Hybrid
Answers
C.
Hybrid
D.
iterative
Answers
D.
iterative
Suggested answer: D