A project manager has just been hired to lead a project team in a hybrid environment. The team is working on a group of critical projects.
What should the project manager do to ensure the right environment and authority are in place to effectively deliver the projects?
A.
Create a project steering committee aligned with existing organizational structures.
B.
Develop a detailed project management plan to share with project resources.
C.
Develop a detailed risk log and share it with all of the project stakeholders.
D.
Appoint a self-organizing project team that is not influenced by organizational factors.