Question 808 - PMP discussion

Report
Export

The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements.

How should the project manager address this situation?

A.
Collaborate with the compliance team member to review and prioritize the requirement's delivery.
Answers
A.
Collaborate with the compliance team member to review and prioritize the requirement's delivery.
B.
Add the new compliance requirement to the backlog as the technical team does not have any capacity.
Answers
B.
Add the new compliance requirement to the backlog as the technical team does not have any capacity.
C.
Include the compliance lead in the stakeholders list and wait for the next status meeting.
Answers
C.
Include the compliance lead in the stakeholders list and wait for the next status meeting.
D.
Ask the team to include the compliance requirement in the current sprint and deliver it.
Answers
D.
Ask the team to include the compliance requirement in the current sprint and deliver it.
Suggested answer: A